The complete productivity toolkit
- Standalone offline browser tracker with editable daily production, project filters, CSV export and JSON backup
- Excel workbook for 200 activity lines with an automatic KPI dashboard and rolling 12-week trend
- Earned MH, actual crew MH, MH variance, labor productivity % and plan attainment
- Print-ready field production sheet, quick-start guide and buyer license
- One ZIP download; no monthly subscription; files can be used without a cloud account
Understand the math: Installed quantity × your allowed labor hours per unit = earned labor hours. Earned ÷ actual crew-hours = productivity. For example, 100 LF × an illustrative 0.25 MH per LF ÷ 24 actual MH = 104.2% productivity and +1 MH variance.
All benchmarks are entered by the buyer, not supplied as verified industry standards. Account for changed scope, materials, rework, access and other jobsite conditions.